Update estimation process with two-factor estimation.
Browse files Browse the repository at this point in the history
  • Loading branch information
jonathanknowles committed Dec 2, 2021
1 parent 4ad8c70 commit 7f601d6
Showing 1 changed file with 151 additions and 49 deletions.
200 changes: 151 additions & 49 deletions docs/process/Estimation-Process.md
Original file line number Diff line number Diff line change
Expand Up @@ -27,73 +27,130 @@ below the estimate. These assumptions translate to risks - because if
they turn out to be incorrect, then they will add more time to the
task.

It's also possible to provide confidence intervals around an
estimation to quantify the uncertainty. For example, a development
task could be estimated to take 30 hours expected, +20 hours worst
case, -5 hours best case. However even then, how often do we expect
that actual time will come in longer than "worst case?"
## Capturing uncertainty in our estimates

## Story points estimates
One common way to express an estimate for a given task is to give a single
number: the number of remaining days of effort the task owner believes that he
or she will require to finish that task.

We accept that accurate estimation is hard, for multiple reasons, so
instead adopt the "just in time" planning technique from XP.
However, a single number alone is unable to capture the degree of confidence or
uncertainty the author of an estimate has. To allow estimate authors to record
their confidence or uncertainty, we need a bit more information.

This uses unitless "story points" for estimation of each
ticket. Possible story point values are on the Fibonacci sequence:
1, 2, 3, 5, 8, 13.
Therefore, we attach to each task a **pair** of estimates:

The idea is that these point values represent task size in an abstract
way. An estimate in time for a task can be calculated from the
estimate in story points divided by the project velocity, adjusted
according to staff availability, other factors, etc.
- **Most-probable estimate (days)**: the number of remaining days of effort the
task owner believes he or she will most likely need to finish that task.

The decision on whether a task is included in the next sprint is
based on its points estimate and the project velocity.
- **Most-pessimistic estimate (days)**: the number of remaining days of effort
the task owner believes he or she will need to be 90% of confident of
finishing that task, given a pessimistic appraisal of the situation, and
taking into account all of the potential things that could go wrong.

This approach is clearly a **gross simplification of reality**, and so
we need to be very careful not to produce garbage estimates.
Note that it's impossible (in general) to predict all the things that could go
wrong with a task. This is why estimates are estimates, and not commitments.
Pilots and co-pilots should feel free to give estimates based on their personal
experience. They may use their accumulated knowledge of how long similar tasks
have taken in the past to develop new estimates.

### Points
The **deviation** between the most-probable estimate and most-pessimistic
estimate allows the authors of each estimate to express their degree of
uncertainty in the estimate, and it allows people viewing the estimates to have
insight into that uncertainty.

| Points | Size |
| -----: | ----------------------------------------------- |
| 1 | |
| 2 | |
| 3 | |
| 5 | |
| 8 | |
| 13 | |
| > 13 | This ticket needs to be split up further. |
A very large deviation between the most-probable and most-pessimistic estimate
tells us that the author is very uncertain in their estimate. We might use
this information to take action, for example, by breaking up a task into
smaller, more well-defined pieces.

### Each _Task_ ticket has an estimate
It's important to realize that:

We assign an estimation to every single task ticket. If there's no
estimate, then it can't be added to the sprint.
- These estimates pertain to the number of days of remaining effort required to
perform that task **in isolation**. If two or more tasks are performed in
parallel, with context switching, then we need to keep the additional cost of
that context switching in mind.

### Ticket must be ready to estimate before estimation
- These estimates refer to a number of days **remaining**, and as such they
should be regularly updated as circumstances change, rather that set in stone
and left unchanged.

If there is not enough information about a task ticket, then the
estimation will be rubbish. So before estimation starts we need:
## Guidelines for creating estimates

1. The _Task_ ticket is linked to a _User Story_ ticket.
2. The ticket description contains adequate information about what is
expected to be done.
3. The ticket includes acceptance criteria.
4. The ticket is sufficiently small to estimate.
5. Task dependencies are defined with jira issue links.
- Estimates should only be created and updated by the pilot and co-pilot
responsible for a given task.

## Team Estimation
- Estimates should be created only after a _Task_ ticket has entered the
"READY" state. This means that a task should not be estimated if either the
pilot or the co-pilot are unclear on what must be done.

Story point estimations are done by the development team together in
the [[Meetings|sprint planning meeting]].
This implies that:

We use the [Pointing Poker](https://www.pointingpoker.com/) tool to
facilitate estimation sessions.
- The _Task_ ticket should have a complete set of acceptance criteria.

The team should agree on a single number. If they don't then someone
is missing some information about the task.
- The _Task_ ticket should have a clear design that the pilot and co-pilot are
capable of estimating. Justification: there are many possible designs for a
given set of acceptance criteria. The time to deliver a task will depend very
strongly on the design that is chosen.

This practice lets us share knowledge about tasks.
- The _Task_ ticket should be linked to a _User Story_ ticket, **if** it
pertains to a user story. (It's important to note that not all tasks must
have a corresponding user story. In the case of technical debt tasks or pure
refactoring tasks, it might not be practical to even identify a user story.)

- The _Task_ ticket is sufficiently small to estimate.

- Task dependencies are defined with Jira issue links.

## Process for updating estimates

One of the main benefits of estimation is that both project management and other
team members can gain visibility on how much time might be required to bring
certain tasks to completion.

Since we have one project planning meeting per week, it makes sense to update
our estimates at around the same frequency.

Before each project planning meeting (currently on Wednesday), each team member
should:

- Identify the tasks he or she is currently working on, in JIRA.

- Make sure that each task has an updated pair of estimates that best reflect
their current understanding of how much remaining time would be required to
bring these tasks to completion.

## Interpreting estimates

Estimates do not represent commitments on behalf of those who create them.

The actual time required to finish tasks, when compared to initial estimates,
can vary wildly, with some tasks taking many times longer than initially
predicted.

This factor: the actual time divided by the estimated time, is often known as
the "blowup factor".

There is some research to indicate that the "blowup factor" (actual time
divided by estimated time) can be reasonably modelled using a log-normal
distribution. See https://erikbern.com/2019/04/15/why-software-projects-take-longer-than-you-think-a-statistical-model.html

TODO:

- [ ] When we have a task with a chain of dependent tasks, devise an automated
method of calculating a most-probable estimate and a most-pessimistic
estimate for the entire chain of tasks. This method might use the log-normal
distribution model suggested above in order to capture the possible blowup
factor for the entire chain.

- [ ] When we have a release that contains large numbers of tasks with
dependencies between them, devise an automated method of determining the most
likely critical paths required to deliver the release, and a method of
calculating a most-probable estimate and a most-pessimistic estimate for
delivering the entire release.

In some situations, there will be one obvious critical path, but in more
complex situations, there may be multiple contenders for the critical path, and
the critical path may change as we make progress through a release.

## Implicit acceptance criteria

Expand Down Expand Up @@ -129,6 +186,38 @@ main task and linked.
We have found that Jira _subtasks_ aren't especially useful. They just
make things confusing, so avoid using them.

# Other methods of estimation

## Story points estimates

This method uses unitless "story points" for estimation of each
ticket. Possible story point values are on the Fibonacci sequence:
1, 2, 3, 5, 8, 13.

The idea is that these point values represent task size in an abstract
way. An estimate in time for a task can be calculated from the
estimate in story points divided by the project velocity, adjusted
according to staff availability, other factors, etc.

The decision on whether a task is included in the next sprint is
based on its points estimate and the project velocity.

This approach is clearly a **gross simplification of reality**, and so
we need to be very careful not to produce garbage estimates.

## Team Estimation

Story point estimations are done by the development team together in
the [[Meetings|sprint planning meeting]].

This method can use the [Pointing Poker](https://www.pointingpoker.com/) tool
to facilitate estimation sessions.

The team should agree on a single number. If they don't then someone
is missing some information about the task.

This practice lets us share knowledge about tasks.

## Updating estimations

By rights, the estimation of a ticket should not change once the
Expand All @@ -139,6 +228,19 @@ suggested, then the team velocity will decrease. The idea is that in
theory the velocity figure records under-estimation tendencies of the
team, so that future sprints may be better planned.

### Points

| Points | Size |
| -----: | ----------------------------------------------- |
| 1 | |
| 2 | |
| 3 | |
| 5 | |
| 8 | |
| 13 | |
| > 13 | This ticket needs to be split up further. |


## TODO: Put remaining time on ticket

- [ ] Write process for updating tickets with "remaining time" value.