Meetings

November 11th, 2015

Manny absent (unknown)

Review

  • Items complete for hand in this Friday:
    • Navigation Diagram - Steve
    • Report Designs - Rob
    • Design-Level Class Diagram - Peter
    • UI Prototypes - Nicole
    • Business Logic - Nicole
    • Data Validation - Rob, Steve, Dan, John, Peter, Nicole
  • Items requiring updates for hand in this Friday:
    • Data Dictionairy - Dan
    • ERD - John. Dan to review
    • Deployment Diagram - Manny. John to message Manny to let him know necessary changes. John completed this.
    • Peter to put all documents together once these are complete

Moving forward

  • 4 weeks to complete implementation
  • Created a preliminary list of implementation items that need to be tackled in the near future
  • John created ASP.NET solution and set up config and migration during meeting
  • John demo'd how to view Blame, to keep track of what people are working on and their commits

November 18th, 2015

All Members Present

Review

Work Period from November 11th - November 18th

Member Worked On Hours This Week Total Hours for Implementation
Dan Nil 0 0
John re-set up config, code first db creation, mock data, assisting members 6 6
Manny Nil 0 0
Nicole controller creation, re-created solution 7 7
Peter assisting members, game controller functionality, troubleshooting, testing 5 5
Rob Nil 0 0
Steve Nil 0 0

During the Meeting

  • Added to the list of implementation items that need to be tackled in the near future
    • Indicated which items on the list were started and which were complete
  • John demo'd making branches in git hub as a refresher, and explained how git pull requests work
  • branch names should include member name and brief description of what they are working on (eg. nicole_controllers)
  • John demo'd adding columns to database using Migration
  • Nicole let all members know that if anyone was unsure of where to start they could message her for suggestions

Moving forward

  • 3 weeks to complete implementation
  • Members asked to keep a broad-strokes log of what they worked on and how many hours they have put into the project
    • This information will be added to our meeting minutes
  • Discussed that all members will be required to download the solution tonight and run it to make sure there are no issues
    • Any members with issues running the solution are directed to contact John for assistance
  • Discussed that there will be a minimum of 4 hours of work each week expected from all members

Next Meeting: November 25th

November 25th, 2015

All Members Present

Review

Work Period from November 11th - November 18th

  • on November 23rd, Nicole sent out a message indicating to all members that at the rate we were working the project would not get complete
    • switching from the honour system with a minimum number of hours put in to each person has an assigned task they must have complete by December 2nd
      • Nicole to continue working on GUI
      • John to continue working on user functionality
      • Peter to continue working on Game controller and potenially pick up Review controller
      • Dan to take over Order Controller from Manny (unintentionally switched)
      • Manny to be responsible for Friendship Controller
      • Rob to be responsible for Report Controller
      • Steve to be responsible for Events Controller
Member Worked On Hours This Week Total Hours for Implementation
Dan Upgraded ERD, review MVC 4 4
John mock data, account controller, consulting 13 18
Manny validation, order controller, friendship controller 9 9
Nicole GUI, Headers (3), Partial Views 9 16
Peter Game Controller, Consulting, Starting review controller 19 24
Rob review MVC 4 4
Steve nil 0 0

During the Meeting

  • Each member indicated the number of hours they worked and what they worked on, this is noted in the above table
  • Nicole asked members what they needed in order to start being involved in the project
    • some members unfamiliar with or need a refresher in MVC
    • Peter noted that the Game controller is mostly complete and that people can look at that code for examples

Moving forward

  • Added a new channel in Discord for members to put a note of what they are blocked on, so that other members may respond with help
  • Members reminded that after their controller is complete that unit tests will be required to be written
  • Milestones added to the README file for day to day requirements of members.
    • Members required to add their initials to each milestone when complete so we can monitor how people are doing

Next Meeting: December 2nd

December 2, 2015

Manny absent (wife giving birth)

Review

Work Period from November 18th - December 2nd

  • Most members met the milestone for having half their controller done by Sunday November 29th
  • Steve switched from Event controller to Client Documentation
Member Worked On Hours This Week Total Hours for Implementation
Dan Order controller 21.5 25.5
John User/Address controller 20 38
Manny Friendship controller 13 21
Nicole GUIs 15 31
Peter Game/Review controller 20 44
Rob Report controller 13 17
Steve Documentation 15 15

During the Meeting

  • John discussed issues he's having with User controller
  • Peter mentioned that he was waiting on wish list to do the library page, should be able to start it now
  • Rob waiting for data for report views
  • Steve will post what he has for client/employee documentation
  • Dan all methods show views, need to connect the view to controller
  • Nicole has done what Gui's were ready to be done.

Moving forward

  • Nicole can do User/Address/Report views
  • Each member to write unit tests for their own controller
  • Each member to add documentation comment to the class for their controller and any methods that are missing them
  • Some views are unused and can be deleted by the member that worked on that controller.

Next Meeting: December 9th

December 9, 2015

All members present

Review

  • all portions of the program are nearly complete, there are just a few items missing

Work Period from December 2nd - December 9th

Member Remaining Work Hours This Week Total Hours for Implementation
Dan Unit tests, edit Steve's documentation 13.5 25.5
John Unit tests, schema change, ZIP file?, preferences 25 38
Manny Unit tests 0 21
Nicole 2 report, events, and orders GUIs 14 45
Peter Unit tests, bug fix, downloads 17.5 61.5
Rob Unit tests, member side events 15 32
Steve member events document, updating images in documentation 13 28

During the Meeting

  • Went over message that Hyslop emailed out earlier, to see what points we were missing
  • remaining points were delegated and given a deadline
  • changed number of login attempts from 5 to 3, as per email

Moving forward

  • Members to have their remaining work done by Saturday December 12th

Next Meeting: December 9th

Date Item Signoffs
November 25, 2015 Discord Meeting DH JS ML ND PT SB
November 27, 2015 Manditory Class Attendance DH JS ML ND PT RS SB
November 28, 2015 Half of assigned controllers completed DH JS ML ND(N/A) PT RS
December 2, 2015 Assigned controllers completed (with views) ML
December 9, 2015 Unit Tests for Assigned controllers completed
December 9, 2015 Technical & Client Documentation
December 9, 2015 Installer CD for server
December 11, 2015 Final Due Date